Short-time scheduling

 0    16 flashcards    dklekowski
mp3 indir Baskı oynamak kendini kontrol et
 
soru English cevap English
Types of short-term scheduling
öğrenmeye başla
Forward scheduling and backward scheduling
Forward scheduling
öğrenmeye başla
begins the schedule as soon as the requirements are known; often builds up WIP; jobs performed to customer order, schedule can be accomplished even if due date is missed
Backward Scheduling
öğrenmeye başla
begins with the due date of the final operation, schedules jobs in reverse order, used in many manufacturing environments; ex. catering
Goals of short-term scheduling
öğrenmeye başla
minimize completion time, maximise utilisation, minimise WIP inventory, minimise customer wait time
process-focused work centres
öğrenmeye başla
high variety, low volume, mate-to-order, different materials and processing for each product, complex production planning and control, production scheduling aspects
Loading Jobs in Work Centres
öğrenmeye başla
assigning jobs to work centres; approaches: input-output control, Gantt charts, assignment method
Input-output control
öğrenmeye başla
CONWIP - constant WIP; for given average output rate, try to keep L low and constant then W will be short and constant; Little's formula
Gantt Load chart
öğrenmeye başla
shows relative workload in facility, negatives: does not account for unexpected events, must be updated regularly
Assignment Method
öğrenmeye başla
occurs in many environments: resources-jobs, planes-gates, course-rooms); type of binary linear programming model
Priority rules for Dispatching Jobs (sequencing)
öğrenmeye başla
FCFS, EDD, SPT, LPT, CR
FCFS
öğrenmeye başla
First come first serve; the first job to arrive at a work centre is processed first
EDD
öğrenmeye başla
earliest due date; the job with the easiest due date is processed first
SPT
öğrenmeye başla
shortest processing time first
LPT
öğrenmeye başla
longets processing time first
CR
öğrenmeye başla
critical ratio; the ratio of time remaining to required work time remaining is calculated and jobs are schedules in order of increasing ratio; CR = time remaining/work days remaining -> process jobs with the smallest CR first
Criteria to evaluate priority rules
öğrenmeye başla
Average Completion Time= Sum of flow times / # jobs; Utilisation = Sum process time / sum flow time; Average number of jobs in system Sum Flow time /Sum processing time; average jobs lateness = sum late times / number of jobs